The County issued the invitation to bid in February 2025, held the pre-bid site walk on March 5, 2025, and opened bids on March 26, 2025. Pay Dirt, LLC built the project in 2026, working the upstream practices first while the outlet question was resolved with MDE, then replacing the pond outfall pipe on June 8, 2026, and adding a second crew to finish by the June 30, 2026 deadline. About 8,500 cubic yards of excavated soil were reused for the County's North County Park ballfields instead of being hauled off site. MDE's Secretary visited the site on June 4, 2026.
Sustainable Science helped prepare the SWPPP and notice of intent, attended the kickoff meeting, inspected the outfall pipe replacement, and handled regulatory coordination. The punch list was issued on July 2, 2026, and MDE's final inspection report, signed August 31, 2026, cleared project closeout. Pay Dirt subcontracted the as-built survey to Sustainable Science, which delivered the signed and sealed as-built plan on September 2, 2026 and is addressing the Center for Watershed Protection's review comments.