The completed work restored 970 linear feet of eroding shoreline at Cheston Point with 5,000 tons of clean washed sand, 3,700 tons of stone in nearshore breakwaters, and 25,850 square feet of planted tidal marsh vegetation. As the sand went in, Sustainable Science observed the first embayment shaping up as predicted and the raised stone blocking yacht wakes. After the post-construction survey in October 2025 the firm found that the constructed work matched the design exceptionally well, and it issued signed and sealed as-built plans at the end of that month.
In January 2026 Sustainable Science submitted the as-built plans, baseline photographs, and an adaptive management and maintenance plan to MDE, the Corps, the Maryland Department of Natural Resources, and the National Marine Fisheries Service as the first-year monitoring submission, and the Corps inspected the site and confirmed in June 2026 that the constructed work complies with the permit. Under the plan SERC maintains the shoreline for a minimum 15-year project lifespan, and Sustainable Science monitors the marsh each spring and fall and compiles annual reports to MDE, the Corps, and NMFS for five years.